Identification of Supplier Selection Criteria and Risk Approach for Egyptian Contractors
International Journal of Emerging Technology and Advanced Engineering • 2014
Publication Information
Authors
Manal S. AbdelHamid, Wafaa M. Arandah, Tarek M. Attia, Osama A. Hosny, Samia A. Mohammed
Keywords
Construction Supply Chain, procurement
management process, procurement risk, risk management,
supplier selection criteria.
Journal
International Journal of Emerging Technology and Advanced Engineering
Publisher
Emerging Technology and Advanced Engineering
Volume
4
Issue
2
Pages
13-18
publication.type
International
Paper Link
Not Available
Supplementary Materials
Not Available
Abstract
In construction sector, contractors in general are
facing unprecedented challenges to comply with the estimated
time and budget of their projects. These challenges increased
due to political unrest in Egypt since 2011. As a result,
contractors need to apply more strict approach to risk
management to avoid cost overruns and expected delays of
payments especially in governmental projects. The goal of this
research is to identify the current risk management approach
for Egyptian contractors. The paper emphasizes the
contractor criteria for supplier selection to reduce expected
risks. The study involves a questionnaire survey and a series
of interviews with contractors. Main elements identified
include supplier selection criteria, suppliers’ qualifications,
logistics, common risks, and the application of formal risk
management methods.
facing unprecedented challenges to comply with the estimated
time and budget of their projects. These challenges increased
due to political unrest in Egypt since 2011. As a result,
contractors need to apply more strict approach to risk
management to avoid cost overruns and expected delays of
payments especially in governmental projects. The goal of this
research is to identify the current risk management approach
for Egyptian contractors. The paper emphasizes the
contractor criteria for supplier selection to reduce expected
risks. The study involves a questionnaire survey and a series
of interviews with contractors. Main elements identified
include supplier selection criteria, suppliers’ qualifications,
logistics, common risks, and the application of formal risk
management methods.