Finance-Based Scheduling: Tool to maximize Project Profit using Genetic Algorithms
Journal of Construction Engineering and Management • 2005
Publication Information
Authors
Elazouni, A., and Metwally, F.
Keywords
Computer aided scheduling; Financial management; Algorithms; Optimization models; Construction
management.
Journal
Journal of Construction Engineering and Management
Publisher
ASCE
Volume
Vol. 131
Issue
No. 4, April (2005)
Pages
pp. 400 – 412.
publication.type
International
Paper Link
Not Available
Supplementary Materials
Not Available
Abstract
Contractor’s ability to procure cash to carry out construction operations represents a crucial factor to run profitable business.
Bank overdrafts have always been the major source to finance construction projects. However, it is not uncommon that bankers set a limit
on the credit allocated to an established overdraft. Bankers’ interest rates and consequently contractors’ financing costs are basically
determined based on the allocated credit limits. Furthermore, project indirect costs are directly proportional to the project duration which
is affected by the allocated credit limit. Thus, the credit limit affects project financing costs and indirect costs which in turn affect project
profit. However, finance-based scheduling produces financially executable schedules at specified credit limits while maintaining the
demand of time minimization. Thus, finance-based scheduling provides a tool to control the credit requirements. This control enables
contractors to negotiate lower interest rates which reduce financing costs. Thus, finance-based scheduling enables contractors to reduce
project indirect costs and financing costs. This paper utilizes genetic algorithm’s technique to devise finance-based schedules that
maximize project profit through minimizing financing costs and indirect costs.
Bank overdrafts have always been the major source to finance construction projects. However, it is not uncommon that bankers set a limit
on the credit allocated to an established overdraft. Bankers’ interest rates and consequently contractors’ financing costs are basically
determined based on the allocated credit limits. Furthermore, project indirect costs are directly proportional to the project duration which
is affected by the allocated credit limit. Thus, the credit limit affects project financing costs and indirect costs which in turn affect project
profit. However, finance-based scheduling produces financially executable schedules at specified credit limits while maintaining the
demand of time minimization. Thus, finance-based scheduling provides a tool to control the credit requirements. This control enables
contractors to negotiate lower interest rates which reduce financing costs. Thus, finance-based scheduling enables contractors to reduce
project indirect costs and financing costs. This paper utilizes genetic algorithm’s technique to devise finance-based schedules that
maximize project profit through minimizing financing costs and indirect costs.